29 Aug 2016
Final Council inspection – We are OPEN !
10 Aug 2016
Pens have arrived and are being installed
31 July 2016
Sorry, it’s been a while since last update…
Wall panels on, plaster installed.
Currently being held up by supplier issues. The pens originally scheduled to arrive 9 July – they are now scheduled for 6 Aug 2016.
But it’s given me a chance to do some painting 🙂
15 June
Roof on !
1 June
Roof trusses delivered
26 May 2016
Frame delivered
17 May 2016
Concrete slab poured
19 Apr 2016
Building permit granted
29 Feb 2016
Building Application submitted
17 Feb 2016
Building plans finalised
20 Jan 2016
Final approval granted by council
1 Dec 2015
Plans submitted to Council for review
20 Oct 2015
Draftsman employed to draw up final plans
14 Oct 2015
Ballarat City Council has issued planning permit to operate a cattery